[Completed] Monthly Production Patch Maintenance – Sunday, 10/14/12

The October Server Patch Maintenance has been completed at 10:55 a.m.

The next scheduled maintenance is a Quarterly, the Pre-Production tentatively set for 11/1/2012 from 7 am to 9 am, and Production Server Maintenance tentatively set for 11/11/2012. A separate blog will be posted, prior to the maintenance performed.

The monthly production patch maintenance is scheduled for Sunday, October 14, from 3:00 AM to 12:00 PM. Most services may be intermittently or entirely unavailable, including:

  • Email
  • Personal and departmental file shares (on Alexandria and Merlin2)
  • Database applications that include Cascade
  • Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
  • vDesk
  • Print Services
  • Merlin2 server migration between 2:30am Saturday morning and 2:30am Sunday morning older version of user files may appear due to the data migration. At the end of this migration and period of time the files will be back up to date.

An update will be posted once server maintenance has been completed.

[Completed] Pre-Production Patch Maintenance Thursday the 4th of October 2012, 7:00 a.m. to 9:00 a.m.

UPDATE:  Server patching for pre-production system has been completed.

On Thursday the 4th of October 2012, from 7:00 AM – 9:00 AM most pre-production servers are to be patched. This means that most test systems may be intermittently or entirely unavailable during this time. Most users will not be impacted, as most users do not have access to these pre-production servers.

This should not affect any production services such as:

Email, Personal and departmental file shares, Database applications, Web services, Print Services, and vdesk.

A follow up email and update to the blog will be posted once Pre-Production Patch Maintenance has been completed.

Alexandria and some test/development server resources temporarily unavailable

Due to the storage migration and expansion we are experiencing issues with Alexandria and selected VM test/development servers. Some files saved after the 9th of August, 2012 on Alexandria may not be accessible until 8 am tomorrow morning due to the server backup restores.

Also, some servers located in the test and development portion of VM, may also not be accessible until further notice, in part caused by storage array issues.

[Completed] Quarterly Production Patch Maintenance 12th August 2012, from 3:00 a.m. to 4:00 p.m.

Most servers and services for the quarterly patch maintenance have been completed to exclude Alexandria and some test/development servers. A separate notification will be sent in TS Alerts about this.

The quarterly production patch maintenance is scheduled for Sunday the 12th of August 2012, from 3:00 AM to 4:00 PM. Most services, may be intermittently or entirely unavailable, including:

  • Email
  • Alexandria to the VMware server upgrade
  • VMware storage array upgrade
  • Personal and departmental file shares (on Alexandria and Merlin2)
  • Database applications: Cascade, FAMIS, Millennium, and Banner
  • Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
  • Optimize
  • vDesk
  • Print Services

An update will be posted once Server Maintenance has been completed.

[Completed] Pre-Production Patch Maintenance Thursday the 2nd of August 2012, from 7:00 am to 9:00 am

The Pre-Production Patch Maintenance has been completed at 9:00 am., and all servers patched during this time period are back online. Next Sunday the 12th of August is a scheduled Quarterly Patch Maintenance Window, and a separate blog will be posted.

On Thursday the 2nd of August 2012, from 7:00 AM – 9:00 AM most pre-production servers are to be patched. This means that most test systems may be intermittently or entirely unavailable during this time. Most users will not be impacted, as most users do not have access to these pre-production servers.

This should not affect any production services such as:

Email
Personal and departmental file shares (on Alexandria and Merlin2)
Database applications: Cascade, FAMIS, Millennium, and Banner
Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
Print Services
vDesk

A follow up email and update to the blog will be posted once Pre-Production Patch Maintenance has been completed.

[Completed] Quarterly Production Patch Maintenance 10th June 2012, from 3:00 a.m. to 4:00 p.m.

The Quarterly Production Patch Maintenance was completed at 4:20 pm. The next production patch maintenance will be a monthly and is tentatively scheduled for the 15th of July 2012.

The quarterly production patch maintenance is scheduled for Sunday the 10th of June 2012, from 3:00 AM to 4:00 PM. Most services, may be intermittently or entirely unavailable, including:

  • Email
  • Service pack 3 upgrade to the Exchange 2007 environment
  • VMware upgrade to ESXi5
  • Personal and departmental file shares (on Alexandria and Merlin2)
  • Database applications: Cascade, FAMIS, Millennium, and Banner
  • Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
  • vDesk
  • Print Services

An update will be posted once Server Maintenance has been completed.

[Completed] Pre-Production Patch Maintenance Thursday the 7th of June 2012, from 7:00 am to 9:00 am

The Pre-Production Patch Maintenance has been completed at 9:00 am., and all servers patched during this time period are back online. This Sunday the 10th of June is a scheduled Quarterly Patch Maintenance Window, and a separate blog will be posted.

On Thursday the 7th of June 2012, from 7:00 AM – 9:00 AM most pre-production servers are to be patched. This means that most test systems may be intermittently or entirely unavailable during this time. Most users will not be impacted, as most users do not have access to these pre-production servers.

This should not affect any production services such as:

Email
Personal and departmental file shares (on Alexandria and Merlin2)
Database applications: Cascade, FAMIS, Millennium, and Banner
Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
Print Services
vDesk

A follow up email and update to the blog will be posted once Pre-Production Patch Maintenance has been completed.

Patch Server Maintenance May 2012

No Patch Maintenance scheduled for the month of May, do to student Study period and Finals week. The next scheduled Patch Maintenance Window will be in June 2012. There will be a Quarterly Server Patch Maintenance in the Month of June. The June Patching will be for Pre-production servers on the 7th of June 2012, from 7 a.m. to 9 a.m., and Production servers Patch Maintenance will be on the 10th of June 2012 from 3 a.m. to 4 p.m.

[Completed] Production Monthly Patch Maintenance Sunday the 8th of April 2012, from 3:00 am to 12:00 pm

[Completed] The Monthly Patch Maintenance was completed at 11:10 a.m. All servers and services taken down for this maintenance period are up and back online. A notification of the next scheduled maintenance will be posted.

The monthly patch maintenance is scheduled for Sunday the 8th of April 2012, from 3:00 AM to 12:00 PM. Most services, may be intermittently or entirely unavailable, including:

  • Email
  • Personal and departmental file shares (on Alexandria and Merlin2)
  • Database applications: Cascade, FAMIS, Millennium, and Banner
  • Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
  • vDesk
  • Print Services

An update will be posted once Server Maintenance has been completed.

[Completed] Pre-Production Patch Maintenance the 5th of April 2012, 7:00 a.m. to 9:00 a.m.

The Pre-Production Patch Maintenance has been completed at 8:50 a.m., and all servers patched during this time period are back online. This Sunday the 8th of April is a scheduled Monthly Patch Maintenance Window, and a separate blog will be posted.

On Thursday the 5th of April 2012, from 7:00 AM – 9:00 AM most pre-production servers are to be patched. This means that most test systems may be intermittently or entirely unavailable during this time. Most users will not be impacted, as most users do not have access to these pre-production servers.

This should not affect any production services such as:

Email
Personal and departmental file shares (on Alexandria and Merlin2)
Database applications: Cascade, FAMIS, Millennium, and Banner
Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
Print Services
vDesk

A follow up email and update to the blog will be posted once Pre-Production Patch Maintenance has been completed.

[Completed] Production Quarterly Patch Maintenance Window, 11th March 2012, 3:00 a.m. to 4:00 p.m.

[Completed] The Production Patch Maintenance was completed at 10:45 am. The next production patch maintenance window is scheduled for Sunday the 15th of April, 2012.

The monthly patch maintenance is scheduled for Sunday the 11th of March 2012, from 3:00 AM to 4:00 PM. Some services may be intermittently or entirely unavailable, including:

  • Email
  • Personal and departmental file shares (on Alexandria and Merlin2)
  • Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
  • vDesk

Database applications: Cascade, FAMIS, Millennium, and Banner should not be affected. A followup will be posted upon completion of this scheduled patch maintenance window.

[Completed] Pre-Production Patch Maintenance, Monthly – Thursday the 1st of March 2012, 7 a.m. to 9 a.m.

The Pre-Production Patch Maintenance was completed at 9:00 am.

On Thursday the 1st of March from 7:00 AM – 9:00 AM most pre-production servers are to be patched. This means that most test systems may be intermittently or entirely unavailable during this time. Most users will not be impacted, as most users do not have access to these pre-production servers.

This should not affect any production services such as:

Email
Personal and departmental file shares (on Alexandria and Merlin2)
Database applications: Cascade, FAMIS, Millennium, and Banner
Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
Print Services
vDesk

A follow up email and update to the blog will be posted once Pre-Production Patch Maintenance has been completed.

[COMPLETED] Production Monthly Patch Maintenance Sunday the 12th of February 2012, from 3:00 am to 12:00 pm

Production patch maintenance for Sunday, February 12th, 2012 has completed as of 11:00 AM PST.

The monthly patch maintenance is scheduled for Sunday the 12th of February 2012, from 3:00 AM to 12:00 PM. Most services, may be intermittently or entirely unavailable, including:

  • Email
  • Personal and departmental file shares (on Alexandria and Merlin2)
  • Database applications: Cascade, FAMIS, Millennium, and Banner
  • Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
  • vDesk
  • Print Services

An update will be posted once Server Maintenance has been completed.

[Completed] Pre-Production Patch Maintenance, Monthly – Thursday the 2nd of February 2012 7 a.m. to 9 a.m.

The Pre-Production Patch Maintenance was completed at 8:50 am.

On Thursday the 2nd of February from 7:00 AM – 9:00 AM most pre-production servers are to be patched. This means that most test systems may be intermittently or entirely unavailable during this time. Most users will not be impacted, as most users do not have access to these pre-production servers.

This should not affect any production services such as:

Email
Personal and departmental file shares (on Alexandria and Merlin2)
Database applications: Cascade, FAMIS, Millennium, and Banner
Web services such as www.pugetsound.edu, cs.pugetsound.edu, and Moodle
Print Services
vDesk

A follow up email and update to the blog will be posted once Pre-Production Patch Maintenance has been completed.